photo1Construction of the new warehouse at the Inspire Community Trust design and build  site continues to move full steam ahead. We are pleased to tell you that the last beam was placed on top of the structural steel frame, more than two full weeks ahead of schedule! During November (as the weather begins to worsen), the concrete floors will be poured. Soon to follow will the construction of the exterior walls followed by the roof installation. The entire building will be weather tight by the end of January so the internal fit can commence.